Analisa Harga Satuan Pekerjaan Furniture Excel

How many days does it take one team to finish 1 m2m squared of a cabinet? (Standard is often 1.5 to 2 days per unit). 3. Equipment & Overhead (Alat & Overhead)

| Component | Material | Coefficient (per m²) | Total Qty for 7.2 m² | Unit | Unit Price (IDR) | Total Cost (IDR) | | :--- | :--- | :--- | :--- | :--- | :--- | :--- | | Body (18mm) | Plywood Meranti | 1.1 m² | 7.92 | Sheet (1 sheet = 2.88 m²) | 285,000 | 2,257,200 | | Back (9mm) | Plywood Far | 1.05 m² | 7.56 | Sheet | 180,000 | 1,360,800 | | HPL Laminate | Tacon | 1.2 m² | 8.64 | Sheet | 350,000 | 3,024,000 | | Edge Banding | 1mm ABS | 4.5 m | 32.4 | Meter | 8,000 | 259,200 | | Handle | Alum. Sliding | 1 | 1 | Set | 450,000 | 450,000 | | Hinge | Soft-close | 6 | 6 | Pair | 35,000 | 210,000 | | Drawer Slide | 45kg | 3 | 3 | Set | 85,000 | 255,000 | | Glue | PVAc | 0.15 | 1.08 | Kg | 30,000 | 32,400 | analisa harga satuan pekerjaan furniture excel

Using a "flat rate" per meter (e.g., 2.5 million per meter) is dangerous for custom designs with expensive internal fittings (like pull-out spice racks). How many days does it take one team

: Typically, an additional 10–15% is added to the subtotal of labor, materials, and equipment to cover operational costs. Resources for Excel Templates Equipment & Overhead (Alat & Overhead) | Component

Mari kita bedah AHS untuk Kitchen Set per meter lari (m1).

| No | Komponen Biaya | Satuan | Jumlah | Harga Satuan | Total Biaya | | --- | --- | --- | --- | --- | --- | | 1 | Bahan baku | unit | 1 | Rp 100.000 | Rp 100.000 | | 2 | Tenaga kerja | jam | 2 | Rp 50.000 | Rp 100.000 | | 3 | Overhead | % | 10% | Rp 20.000 | Rp 20.000 | | 4 | Keuntungan | % | 15% | Rp 30.000 | Rp 30.000 | | | | | | | Rp 250.000 |